LC Water supported head contractor CCB Envico in the design and construction of the new anaerobic digester and biogas handling facilities.
LC Water was responsible for the D&C of the biodome, biogas flare system, chemical dosing facilities, all mechanical installation work, installation of all heating, (package boiler), heat exchange and mixing systems, and commissioning of all of the above.
This project provided LC Water with direct and recent experience in all aspects of anaerobic digestion and biogas generation, biogas handling, flaring, polishing and storage, electricity cogeneration.
The delivery included:
- A Landia pumped/gas mixing system to negate the need for hazardous area rated gas mixing system.
- A double membrane gas holder for biogas storage
- An enclosed flare which permitted use on days of Total Fire Ban
Value: $2.8M